Default DW Home - Built and available.. when to inspect?

There is one David Wilson house of the style we want remaining from the current crop of buildings.

It is £265k but will be discounted to £250k.

We are considering putting down the £250 deposit to reserve it.

No doubt after this, they will look to complete ASAP because its already built and ready to move in to (bar flooring).

Should I state outright that I will want to inspect for snagging?

Just from viewing the property I noticed certain snags like a gap above a power socket, the lawn not being properly laid and some loose tiles on the roof.

If I reserve the house, should I be given the chance to inspect the property right away?
Can I do so as many times as I want?
Then can snagging list be handed it and should the initial problems rectified before we sign the contract and receive the keys?
Or must we sign within the 28 days regardless of the snagging status?

I guess what I am asking is for an explanation of the whole process, beginning from reserving the property.
TheGame7 is offline   Reply With Quote
Old 22nd April 2007, 00:36   #2
Administrator
 
Join Date: Oct 2005
Posts: 904
Tony has a reputation beyond reputeTony has a reputation beyond reputeTony has a reputation beyond reputeTony has a reputation beyond reputeTony has a reputation beyond reputeTony has a reputation beyond reputeTony has a reputation beyond reputeTony has a reputation beyond reputeTony has a reputation beyond reputeTony has a reputation beyond reputeTony has a reputation beyond repute
Default Re:DW Home - Built and available.. when to inspect

TheGame7 wrote:
Quote:

Should I state outright that I will want to inspect for snagging?

If I reserve the house, should I be given the chance to inspect the property right away?
Can I do so as many times as I want?
Then can snagging list be handed it and should the initial problems rectified before we sign the contract and receive the keys?
Or must we sign within the 28 days regardless of the snagging status?
You can ask to snag the property before you exchange contracts, which is good for you as you can easily pull out if there are lots of issues. You could try to get your solicitor to put a clause about the remedial work in the contract.

You are not obliged to exchange, but once you have exchanged you will have to complete.

The house isn't yours and you don't have a legal interest in the property till you exchange, so the inspections will be at the discretion of the developer.

Good luck

Tony
__________________
Get the Snagging Guide for FREE. Snagging Photos.
Visit the consumer forums - for more general consumer advice and information about your consumer rights.
Tony is offline   Reply With Quote
Old 23rd April 2007, 10:46   #3
Member
 
Join Date: Jun 2006
Posts: 31
martynh99
Default Re:DW Home - Built and available.. when to inspect

Agree entirely with Tony re getting the Solicitor to include the remedial work as a clause.
We bought a property 10 months ago from Miller homes and didn't get the chance to snag it before exchanging contracts - 10 months on we're still getting the snags fixed.

Personally, if a builder refused a snagging inspection before exchanging contracts on a completed property, i'd walk away as they're obviously not trustworthy.
martynh99 is offline   Reply With Quote
Reply

Bookmarks

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are Off



All times are GMT +1. The time now is 04:48.
Powered by vBulletin
Copyright © 2000-2009 Jelsoft Enterprises Limited.



Content Relevant URLs by vBSEO 3.3.0

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34