Hi JJ,
I am not sure that I fully understand, but if the builder has served you notice to complete and sets a date then fails to complete then you will be eligible to claim
liquidated damages. The builders avoid having to pay this by only serving notice when they are absolutely certain that completion will not be delayed and tend only to give buyers seven days.
I hoep this helps
Tony